Date |
Device Name |
Quantity |
User |
Remark |
2012.5 to 2012.10 |
Five stations cab assembly line with two robots complement welders bit
Floor assembly, beams sub-assembly fixture
The windscreens and assembly experience with
Automatic semi-automatic on the downline spreader |
34
Sets |
China National Heavy Duty Truck Group Jinan Truck Co., Ltd. |
HOWO-A7 cab (7 models switching Sharing) assembly production lines, robot stations, steel structures, and water and electricity system |
2011.12
~ 2012.4 |
Beams on the front wall assembly fixture
And hoarding after assembly fixture
Front bumper bull beam assembly fixture
After the top beam assembly fixtures, etc. |
19 units |
YTO Fulai Ge Body Co., Ltd. |
The hippocampus ZM2 parts pneumatic fixture |
2012.2 to 2012.5 |
Cab lifting device
Skeleton tailor welded jig
The repair welding rotate fixture
Cab transport trolley |
About 40 sets of |
John Deere Tianjin TEDA factory |
Manual, pneumatic and electrical control fixture, PLC controlled lifting device. |
2012.1 to 2012.4 |
R / F PKG TRAY BKT RH / LH |
1 set |
Futaba Shye Chan Machinery Co., Ltd. |
Spot welding robot workstation |
2011.8 to 2012.1 |
The left / right rear wheel cover plate assembly jig
Left / right posterior longitudinal beam assembly fixture
In the rear floor assembly fixture.
Rear floor assembly fixture
One, two lower body assembly station fixture
Body to assembly twenty-two station fixture
Floor assembly, body assembly off the assembly line spreader |
About 20 sets of |
The Huachen shares Holdings Limited |
A3 four-wheel drive, manual pneumatic clamps, spreader conveyor. |
2011.8 to 2012.1 |
RR DOOR INR1 # ASSY
RR DOOR INR2 # ASSY
RR DOOR TOR ASSY
RR DOOR A / H ASSY
T / LID INR ASSY
T / LID OTR ASSY |
10 units |
South East (Fujian) Motor Co., Ltd. |
SEM V5 project, gas control fixture |
2011.7 to 2012.1 |
Floor frame assembly fixture
Floor assembly a four-station assembly fixture
The floor assembly flip patching fixture (electronically controlled)
The body assembly fixture (PLC control)
Front wall, rear wall, the left and right side panels, roof assembly fixture |
37
Sets |
Foton Zhucheng Automobile Factory |
Of Foton Ollin factory era V5 body installed the wire bonders project, pneumatic power control fixture. |
2011.8 ~
2011.12 |
FR FLOOR SUB COMP SET JIG
FR FLOOR COMP SET JIG
RR FLOOR PNL COMP SET JIG
RR FLOOR FRM COMP JIG
RR FLOOR COMP JIG
RR INN COMP JIG R / L
FR DOOR PANEL SET JIG
RR DOOR PANEL SET JIG |
8
Sets |
Dongfeng Honda Automobile Co., Ltd. |
WDHAC, 2HC project, pneumatic clamps |